How long does the full project take from contract to play?
Quick answer
Typical Roswell residential courts run 8–14 weeks from signed contract to first ball.
Typical Roswell residential courts run 8–14 weeks from signed contract to first ball. Permitting and HOA approval are 3–6 weeks of that. Site work is 2–4 weeks. Surfacing waits for the slab to cure (usually 28 days for concrete, 14 for post-tension) plus weather windows for acrylic application.